Task facts & stats

7 fact-checked facts about tasks and productivity, each with the reason behind it. 5 more are in today's round and join this page after it closes.

Play today's round

The basics

In SMART goals, what does the M usually stand for?

AnswerMeasurable

SMART goals are commonly defined as specific, measurable, achievable, relevant and time-bound.

On a task list, what does ASAP mean?

AnswerAs soon as possible

ASAP is short for 'as soon as possible'.

Going deeper

Which type of chart shows project tasks as horizontal bars along a timeline?

AnswerGantt chart

A Gantt chart lists tasks down the side and draws each one as a bar spanning its start and end dates.

Which 'law' says that work expands to fill the time available for its completion?

AnswerParkinson's law

Parkinson's law was coined by C. Northcote Parkinson in a humorous 1955 essay about bureaucracy.

In project planning, what is a task that must be finished before another can start called?

AnswerA dependency

A dependency links tasks so that one cannot begin (or finish) until another is done.

Expert level

What is the name for the tendency to remember unfinished tasks better than completed ones?

AnswerZeigarnik effect

Psychologist Bluma Zeigarnik reported in the 1920s that interrupted tasks were recalled better than finished ones.

In project management, what does the 'critical path' show?

AnswerThe longest chain of dependent tasks, setting the shortest possible project time

Any delay to a task on the critical path delays the whole project, since those tasks have no slack.

Know these cold?Today's round is five questions like these, 20 seconds each. Your streak and level follow you to every arena.Play today's round